Transportation / Municipal & Federal

SR 9 Emergency Slope Repair

*Emergency stabilization of a 180-foot landslide that closed a state route overnight, with a temporary lane restored in 6 days and a permanent soldier-pile and tieback wall completed in 19 weeks.

SR 9 Emergency Slope Repair
Client
Cascadia Regional DOT
Engineer
Cascade Geotechnical Group
Location
Snohomish, WA
Value
$5M–$25M
Delivery
Emergency Response
Status
Completed
Completed
2025

Spec sheet

By the numbers

Slide length
180 LF of roadway
Debris removed
14,500 CY
Soldier piles
86 piles, 30 in. dia., to 58 ft
Tieback anchors
172 anchors, 220 kips
Wall face
9,800 SF shotcrete and precast panels
Contract value
$8.9 million

Story

Challenge, solution and outcome

Challenge

After 11 days of heavy rain, a hillside above the highway failed on a Friday evening, burying both lanes under 14,500 cubic yards of soil and trees and exposing the failure scarp to continued movement. The route is the only connection for 6,000 residents and a major freight link.

The owner needed a reopening in days, but the hillside remained unstable and further rain was forecast.

Solution

Our emergency crew was on site within 90 minutes of the call, working under floodlights to clear debris with excavators monitored by a geotechnical engineer and slope inclinometers. A one-lane temporary road on a buttress of imported rock was open to escorted traffic on day 6.

The permanent repair was design-built with the owner's geotechnical consultant: a soldier-pile and tieback wall with a shotcrete face and a drained backslope. All emergency force-account documentation was provided to the owner in the format required for federal emergency relief reimbursement.

Outcome

The route reopened to two lanes of traffic on day 133, 17 days ahead of the owner's target. The wall instrumentation shows less than a quarter inch of movement after the first winter.

The crew worked 58,000 hours, including 22 night shifts, with 0 lost-time incidents and the owner received complete reimbursement documentation for the FHWA emergency relief claim.

Safety

Safety highlights

  • 0 lost-time incidents over 58,000 work hours
  • Geotechnical spotter and slope-movement alarms on all debris-removal shifts
  • Night-lighting plan and fatigue-management rules for emergency shifts
  • Escorted one-lane traffic with no public incidents