Quality

An ISO 9001:2015 quality system that follows the work from submittal to turnover.

Quality is a process, not an inspection at the end

Halvorsen Pike maintains a quality management system certified to ISO 9001:2015. Each project begins with a project-specific quality control plan that identifies definable features of work, the tests required, hold points and the person responsible for each step. Plans are submitted to the owner and reviewed at the preparatory meeting for every feature.

Our own certified technicians perform concrete, soil, aggregate and asphalt testing, with ACI, WAQTC and NICET credentials. Results are logged and shared with the owner's inspector within 24 hours, and nonconformances are tracked to closure in the same system we use for submittals.

Three-phase control

How a feature of work moves through QC

  1. STA 0+00

    Preparatory

    Before work starts: submittals approved, materials verified, crews briefed on tolerances and the inspector walks the area with the foreman.

  2. STA 1+00

    Initial

    The first unit of work is inspected in full. The foreman, QC lead and owner agree on workmanship standards.

  3. STA 2+00

    Follow-up

    Continuous inspection and testing, with nonconformances documented, corrected and verified before the work is covered.

  4. STA 3+00

    Turnover

    Final tests, as-built records, warranty documents and O&M training completed before substantial completion.

In practice

What owners see on site

  • 01

    In-house testing

    Certified technicians test concrete, soil and asphalt on the spot, with results available the same day.

  • 02

    Survey and layout control

    Our own survey crews set control, stake work and verify as-builts with GPS and robotic total stations.

  • 03

    Submittal discipline

    Submittals are logged, reviewed and cross-checked against the specifications before ordering.

  • 04

    Weld and reinforcement inspection

    AWS-certified weld inspection and independent rebar placement review before every major pour.

  • 05

    Nonconformance tracking

    Problems are documented, root-caused and closed out, with trends reviewed monthly by management.

  • 06

    Commissioning

    Functional and performance tests are witnessed by the owner and recorded in the turnover package.

Credentials

Certifications

Certifications

Review a sample quality plan

We can send a redacted project quality control plan with your prequalification package.