Skookum Creek Bridge Replacement

*Replacement of a 1960s timber-and-steel river crossing with a three-span, 486-foot prestressed girder bridge, built inside a 14-week fish window while keeping a 9,000-vehicle-per-day detour open.

Skookum Creek Bridge Replacement
Client
Cascadia Regional DOT
Engineer
Northbank Engineering Group
Location
Shelton, WA
Value
$5M–$25M
Delivery
Design-Bid-Build
Status
Completed
Completed
2023

Spec sheet

By the numbers

Total length
486 ft, three spans
Superstructure
WF83G prestressed girders, 7 lines
Foundations
12 drilled shafts, 7 ft dia. x 94 ft deep
Concrete placed
4,850 CY
Reinforcing steel
610 tons, epoxy-coated
Contract value
$18.4 million

Story

Challenge, solution and outcome

Challenge

The existing bridge crossed a salmon-bearing creek with an in-water work window that closed on September 15. The permit allowed no more than 14 weeks of work below the ordinary high-water mark, and the geotechnical report identified a boulder layer at 60 feet that had stopped two earlier shaft attempts on a neighboring structure.

The corridor also carried school bus routes and log trucks. The owner required a signed detour and no closure longer than 45 minutes during school hours.

Solution

We built a 620-foot temporary work trestle in the first three weeks so that shaft rigs, cranes and concrete trucks never entered the channel. Two shaft rigs worked in parallel, one fitted with a rock auger and core barrel for the boulder layer, and crosshole sonic logging was run within 48 hours of every pour so that the engineer could accept shafts without delay.

Girders were set in a single 11-day campaign using a 330-ton crawler crane. We placed the deck in three pours at night with a retarded mix to keep surface temperature inside the specified window, then installed the barrier and approach slabs from a fixed schedule of 45-minute lane closures.

Outcome

The bridge opened to traffic 47 days ahead of the contract completion date and $412,000 under the original contract value. Every in-water activity finished eight days before the fish window closed, and turbidity monitoring recorded no exceedances.

The project logged 0 lost-time incidents over 186,000 hours. The owner scored the final ride quality at 38 inches per mile on the international roughness index, earning the full smoothness incentive.

Safety

Safety highlights

  • 0 lost-time incidents over 186,000 work hours
  • Temporary work trestle eliminated all in-channel equipment operations
  • Daily crane pick plans reviewed by an independent rigging engineer
  • Zero spill events across 14 weeks of over-water work

From the owner

“Halvorsen Pike finished inside a fish window that our own staff considered a stretch, and they did it with no turbidity violations. Their superintendent talked to our inspectors every morning, and nothing came as a surprise.”

Deborah Tran, PE Region Project Engineer, Cascadia Regional DOT