Water
Cedar Ridge Reservoir & Transmission Main
*An 8 million-gallon prestressed concrete reservoir and 7.2 miles of 48-inch welded steel transmission main, built in lava-rock terrain to connect two pressure zones serving 24,000 customers.
- Client
- Cedar Ridge Water District
- Engineer
- Highline Civil Consultants
- Location
- Bend, OR
- Value
- $25M–$100M
- Delivery
- CM/GC
- Status
- Completed
- Completed
- 2020
Spec sheet
By the numbers
- Reservoir volume
- 8 MG, wire-wound prestressed concrete
- Reservoir diameter
- 196 ft, 36 ft sidewall
- Transmission main
- 7.2 miles, 48-in. welded steel
- Rock excavation
- 212,000 CY
- Concrete placed
- 6,100 CY
- Contract value
- $54.3 million
Story
Challenge, solution and outcome
Challenge
More than 40 percent of the pipeline alignment ran through basalt. Early borings suggested a rippable layer, but the CM/GC pricing phase showed continuous rock at 4 to 12 feet along 3.1 miles, a condition that could have cost the owner millions in post-award change orders.
The site sits in a high-desert climate with winter freeze cycles, narrowing the window for tank wire-winding and shotcrete application.
Solution
We commissioned additional borings and seismic refraction surveys during preconstruction, then negotiated a unit price for rock excavation that put hammer and controlled-blasting risk in the GMP rather than leaving it as an unknown. Blast designs were reviewed by the county fire marshal, and vibration was monitored at 31 nearby structures.
Steel pipe was installed in 40-foot joints with field-welded and mortar-lined joints, each inspected by radiographic testing. The reservoir wall was wound in a single heated enclosure to hold the shotcrete cure temperature above 50 degrees through January.
Outcome
The reservoir and main were energized 36 days early and $4.2 million under the GMP, with the owner receiving 100 percent of the savings. The pipeline passed hydrostatic testing at 1.25 times working pressure on the first attempt, and blast vibration stayed below the 0.5 inch-per-second limit at every monitored structure.
The project logged 0 lost-time incidents over 301,000 hours.
Safety
Safety highlights
- 0 lost-time incidents over 301,000 work hours
- Blasting program with licensed blaster and pre-blast surveys of 31 structures
- Trench safety audit weekly with shoring designed for 20-foot-deep sections
- Welding and radiography exclusion zones enforced with a permit system
From the owner
“Putting the rock risk in the guaranteed maximum price during preconstruction took a difficult conversation, and it saved us from the surprises we had on our last pipeline. The tank went in the way they said it would.”