Cedar Ridge Reservoir & Transmission Main

*An 8 million-gallon prestressed concrete reservoir and 7.2 miles of 48-inch welded steel transmission main, built in lava-rock terrain to connect two pressure zones serving 24,000 customers.

Cedar Ridge Reservoir & Transmission Main
Client
Cedar Ridge Water District
Engineer
Highline Civil Consultants
Location
Bend, OR
Value
$25M–$100M
Delivery
CM/GC
Status
Completed
Completed
2020

Spec sheet

By the numbers

Reservoir volume
8 MG, wire-wound prestressed concrete
Reservoir diameter
196 ft, 36 ft sidewall
Transmission main
7.2 miles, 48-in. welded steel
Rock excavation
212,000 CY
Concrete placed
6,100 CY
Contract value
$54.3 million

Story

Challenge, solution and outcome

Challenge

More than 40 percent of the pipeline alignment ran through basalt. Early borings suggested a rippable layer, but the CM/GC pricing phase showed continuous rock at 4 to 12 feet along 3.1 miles, a condition that could have cost the owner millions in post-award change orders.

The site sits in a high-desert climate with winter freeze cycles, narrowing the window for tank wire-winding and shotcrete application.

Solution

We commissioned additional borings and seismic refraction surveys during preconstruction, then negotiated a unit price for rock excavation that put hammer and controlled-blasting risk in the GMP rather than leaving it as an unknown. Blast designs were reviewed by the county fire marshal, and vibration was monitored at 31 nearby structures.

Steel pipe was installed in 40-foot joints with field-welded and mortar-lined joints, each inspected by radiographic testing. The reservoir wall was wound in a single heated enclosure to hold the shotcrete cure temperature above 50 degrees through January.

Outcome

The reservoir and main were energized 36 days early and $4.2 million under the GMP, with the owner receiving 100 percent of the savings. The pipeline passed hydrostatic testing at 1.25 times working pressure on the first attempt, and blast vibration stayed below the 0.5 inch-per-second limit at every monitored structure.

The project logged 0 lost-time incidents over 301,000 hours.

Safety

Safety highlights

  • 0 lost-time incidents over 301,000 work hours
  • Blasting program with licensed blaster and pre-blast surveys of 31 structures
  • Trench safety audit weekly with shoring designed for 20-foot-deep sections
  • Welding and radiography exclusion zones enforced with a permit system

From the owner

“Putting the rock risk in the guaranteed maximum price during preconstruction took a difficult conversation, and it saved us from the surprises we had on our last pipeline. The tank went in the way they said it would.”

Elaine Whitcombe Director of Engineering, Cedar Ridge Water District