Wastewater / Water

Millrace Pump Station

*A 120 MGD regional wastewater pumping station with a 58-foot-deep wet well and 60-inch force main, built in an urban floodplain next to an operating interceptor.

Millrace Pump Station
Client
Treasure Valley Water Reclamation District
Engineer
Sawtooth Engineering Associates
Location
Boise, ID
Value
$25M–$100M
Delivery
Design-Bid-Build
Status
Completed
Completed
2018

Spec sheet

By the numbers

Firm capacity
120 MGD peak
Pumps
Six 700 HP vertical turbine units with VFDs
Wet well depth
58 ft, 64 ft diameter caisson
Force main
5,200 LF of 60-in. steel
Standby power
Three 2.0 MW generators
Contract value
$39.7 million

Story

Challenge, solution and outcome

Challenge

The wet well had to be sunk through 40 feet of saturated gravel and cobbles with a groundwater table two feet below the surface, only 70 feet from an active 84-inch interceptor that could not be shut down.

The station was designed to be fully operational before the spring peak flows of 2018, a date that left no room for slippage.

Solution

We used a caisson sinking method with a bentonite lubricant and deep-well dewatering, setting 36 monitoring points on the interceptor and neighboring buildings. Settlement stayed under 0.4 inches, well below the 1-inch alarm threshold.

While the structure was being built, pumps, switchgear and generators were released for early fabrication and staged off site, so that we could set equipment within three weeks of the building being weathertight.

Outcome

The station passed its 72-hour full-load acceptance test on April 3, 2018, 41 days ahead of schedule, and handled the spring peak flow that year without a bypass event. The force main passed hydrostatic testing at 150 psi with no leaks.

The project closed with 0 lost-time incidents over 219,000 hours.

Safety

Safety highlights

  • 0 lost-time incidents over 219,000 work hours
  • Caisson sinking protocol with rescue plan and gas monitoring
  • Interceptor protection plan with real-time settlement alerts
  • Weekly hot-work permit audits

From the owner

“Sinking a 58-foot caisson 70 feet from an interceptor we could not shut down made everyone nervous. The settlement data never moved, and the station was running before the spring peak.”

Carlos Aguilar, PE Capital Projects Director, Treasure Valley Water Reclamation District