Wastewater

Basin 7 Lift Station Program

*Replacement of seven aging lift stations across a 14-square-mile basin under one CM/GC agreement, using standardized designs and repeatable crews to deliver a station roughly every four months.

Basin 7 Lift Station Program
Client
Three Rivers Sanitary District
Engineer
Willamette Basin Engineers
Location
Salem, OR
Value
$25M–$100M
Delivery
CM/GC
Status
In Progress

Spec sheet

By the numbers

Stations
7 submersible lift stations
Capacity range
1.5 to 9 MGD each
Force mains
4.1 miles, 8 to 24 in. HDPE
Wet well depth
22 to 41 ft
Standby power
Seven diesel generators, 125 to 500 kW
Contract value
$47 million (GMP)

Story

Challenge, solution and outcome

Challenge

The district's seven stations were 40 to 55 years old, with undersized wet wells, obsolete controls and a history of overflows during storm events. All seven sit in residential neighborhoods, and each has to stay in service until the replacement is operational.

Procuring seven stations individually would have meant seven design reviews, seven bid cycles and seven learning curves.

Solution

We worked with the engineer to develop a standard station design with site-specific adaptations, and procured pumps, panels and generators in bulk. A dedicated crew now moves from site to site on a repeatable 16-week sequence, with each station's HDPE force main fusion-welded and pre-tested before the cutover.

Neighbors receive door-hangers 14 days before work begins and a direct line to the project superintendent. Overflow risk is managed by pre-installed bypass pumps with auto-start controls.

Outcome

Three stations are in service as of this writing, each completed 10 to 18 days ahead of its baseline. Standardization has cut the cost per station by 19 percent compared with the district's initial estimate.

The program has logged 118,000 hours with 0 lost-time incidents and no sanitary sewer overflows.

Safety

Safety highlights

  • 0 lost-time incidents over 118,000 work hours to date
  • Residential work-zone plan with pedestrian and school-route protection
  • Excavation and shoring plan for every wet well, reviewed by a PE
  • Bypass pumping tested under load before any cutover