North Fork Bridge Seismic Retrofit
*Seismic strengthening of a 1958 steel-and-concrete river crossing, including pier jacketing, new isolation bearings and a full deck overlay, with the bridge open to one lane of traffic throughout.
- Client
- Three Rivers County Public Works
- Engineer
- Ridgeline Structural Engineers
- Location
- Hood River, OR
- Value
- $5M–$25M
- Delivery
- Design-Bid-Build
- Status
- Completed
- Completed
- 2018
Spec sheet
By the numbers
- Bridge length
- 672 ft, five spans
- Pier retrofit
- 4 piers, steel-jacketed and grout-filled
- Isolation bearings
- 20 lead-rubber bearings
- Deck overlay
- Latex-modified concrete, 28,500 SF
- Reinforcing steel
- 95 tons
- Contract value
- $11.2 million
Story
Challenge, solution and outcome
Challenge
The retrofit design required work around four river piers in a channel with seasonal flows that rose from 600 cfs to more than 4,000 cfs during spring runoff. The bridge was the only crossing for a rural community of 3,200 people and could not be closed.
Original drawings were incomplete, and exploratory work revealed corroded bearing seats and unmarked reinforcement locations that affected the jacket design.
Solution
We worked the piers in a low-flow sequence from July to October, using sheet-pile cofferdams driven with vibratory hammers and dewatered with sumps. A scanned reinforcement survey of each pier was completed before drilling so that the retrofit anchors avoided steel, and the engineer issued revised details within five working days of each discovery.
Bearings were replaced one girder line at a time on synchronized jacks, with live-load monitoring and a single lane open under flagging control. The deck overlay was placed in half-width sections over eight weekends.
Outcome
The bridge was rated to withstand a 1,000-year seismic event and reopened to full capacity 22 days ahead of schedule. The project closed with change orders totaling 2.7 percent of the contract, most of which traced to the incomplete as-builts.
Crews worked 94,000 hours with 0 lost-time incidents, and the county used our as-built survey as the basis for retrofitting two similar bridges.
Safety
Safety highlights
- 0 lost-time incidents over 94,000 work hours
- Fall protection plan for 60-foot pier work, reviewed with each crew daily
- Cofferdam entry procedure with rescue team on site
- Single-lane traffic maintained with zero public incidents